When the present value of the cash inflows exceeds the initial cost of a project, then the project should be:
A) accepted because the internal rate of return is positive.
B) accepted because the profitability index is greater than 1.
C) accepted because the profitability index is negative.
D) rejected because the internal rate of return is negative.
E) rejected because the net present value is negative.
Correct Answer:
Verified
Q16: All else constant, the net present value
Q17: An investment is acceptable if its average
Q18: The advantages of the payback method of
Q19: Net present value:
A)cannot be used when deciding
Q20: The present value of an investment's future
Q22: If a project is assigned a required
Q23: Given that the net present value (NPV)
Q24: In actual practice, managers may use the:
Q25: The internal rate of return is:
A)more reliable
Q26: When two projects both require the total
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents