You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values.What can you conclude?
A) You have incorrectly performed the analysis.
B) You have multiple critical paths.
C) Only one path is optimal.
D) More than one path is optimal.
E) The project will not be completed by the desired time.
Correct Answer:
Verified
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: Here are the data for a time-cost
Q65: You have just used the network planning
Q66: You have collected the data for a
Q68: You know when you have arrived at
Q69: You have just used the network planning
Q70: Popular project management software used in mid-sized
Q71: You have the following time and cost
Q72: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents