Solve the linear programming problem.
-An automotive glass plant must be able to fill orders for 230 truck windshields, 350 auto windshields, and 310 RV windshields. Because the first-shift crews are more experienced, they are each able to make 7 truck
Windshields, 12 auto windshields, and 9 RV windshields. The second-shift crews are able to produce 4 truck
Windshields, 12 auto windshields, and 7 RV windshields. The first-shift crews cost the company $360.00 per
Crew per shift, and the second-shift crews cost $310.00 per crew per shift. The company's facilities will handle at
Most 50 crews on each shift, and they must have at least 10 crews come in to keep the plant running. How many
First-shift and how many second-shift crews should be scheduled to minimize costs?
A) 51 first-shift crews and 17 second-shift crews
B) 28 first-shift crews and 10 second-shift crews
C) 37 first-shift crews and 36 second-shift crews
D) 43 first-shift crews and 24 second-shift crews
Correct Answer:
Verified
Q356: Use the shading capabilities of your
Q357: Graph the solution set of the
Q358: Graph the solution set of the
Q359: Graph the solution set of the
Q360: Graph the solution set of the
Q362: Determine the system of inequalities illustrated
Q363: Determine the system of inequalities illustrated
Q364: The graph shows the region of
Q365: Solve the linear programming problem.
-An airline
Q366: The graph shows the region of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents