Schedule of Activity Costs ​

Question 107

Multiple Choice

Schedule of Activity Costs Schedule of Activity Costs   ​ -A customer service department has the following resolution response time data: Average Response Time First contact 0.25 hr.Service scheduling 0.50 hr.Wait for service 24.00 hrs.Service 1.50 hrs.Total resolution time 26.25 hrs.What is the value-added ratio (rounded to one decimal place)  in this process? A) 5.7% B) 8.6% C) 28.6% D) 91.4%
-A customer service department has the following resolution response time data: Average Response Time
First contact 0.25 hr.Service scheduling 0.50 hr.Wait for service 24.00 hrs.Service 1.50 hrs.Total resolution time 26.25 hrs.What is the value-added ratio (rounded to one decimal place) in this process?


A) 5.7%
B) 8.6%
C) 28.6%
D) 91.4%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents