Solved

When the Lower Assessed Level of Control Risk Approach Is

Question 21

Multiple Choice

When the lower assessed level of control risk approach is used, the final assessment of control risk is made after completing:


A) the procedures to obtain an understanding.
B) the documentation of the understanding.
C) all the planned tests of controls.
D) all the above.