Stone Age Surfboards is a small manufacturer of two types of popular low-tide surfboards, the Graystone and the Lava models. The manufacturing process consists of two departments: fabrication and finishing. The fabrication department has 8 skilled workers, each of whom works
9.25 hours per day. The finishing department has 5 workers, each of whom works a 6-hour shift per day. Each pair of Graystone surfboards requires 2.5 labor hours in the fabrication department and 2 labor hours in finishing. The Lava model requires 4.2 labor-hours in fabrication and 3.6 labor-hours in finishing. The company operates 6 days a week. It makes a per unit profit of $40 on the Graystone model and $60 on the Lava model. The company anticipates selling at least twice as many Lava models as Graystone models.
Use the spreadsheet below for Stone Age Surfboards to answer the following questions) using integer constraints on variables in the optimization models using the standard Solver.
-What is the total number of hours used for the finishing operation?
A) 39.6
B) 34.4
C) 29.2
D) 24.8
Correct Answer:
Verified
Q13: Use the table below to answer
Q14: Use the table below to answer
Q15: Use the table below to answer
Q16: Stone Age Surfboards is a small manufacturer
Q17: Use the table below to answer
Q19: Stone Age Surfboards is a small manufacturer
Q20: Use the table below to answer
Q21: What is the importance of binary variables
Q22: If the Integer Tolerance is set to
Q23: Use the table below to create
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents