In the context of the Critical Path Method (CPM) , the slack time (ST) for an activity is computed as:
A) the latest start (LS) time minus the earliest finish (EF) time.
B) the latest finish (LF) time minus the earliest start (ES) time.
C) the latest start (LS) time minus the earliest start (ES) time.
D) the earliest finish (EF) time minus the latest start (LS) time.
Correct Answer:
Verified
Q15: Which of the following is true of
Q16: Which of the following is true of
Q17: A_is a temporary and often customized initiative
Q18: The activities, their respective immediate predecessors,
Q19: The earliest time that an activity can
Q21: Implementing a new computer-aided design system is
Q22: In the context of projects,_are discrete tasks
Q23: Rose is in charge of advertising
Q24: Which of the following is true of
Q25: If an activity can be completed in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents