Solved

Use the Following Information for the Next 4 Questions

Question 33

Multiple Choice

Use the following information for the next 4 questions.
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Use the following information for the next 4 questions. Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded:   -The variable overhead efficiency variance was A)  $8,000 U B)  $4,000U C)  $2,000 U D)  $4,000 F
-The variable overhead efficiency variance was


A) $8,000 U
B) $4,000U
C) $2,000 U
D) $4,000 F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents