A cost is considered controllable at a given level of managerial responsibility if
A) the manager has the power to incur the cost within a given time period.
B) the cost has not exceeded the budget amount in the master budget.
C) it is a variable cost but it is uncontrollable if it is a fixed cost.
D) it changes in magnitude in a flexible budget.
Correct Answer:
Verified
Q78: A flexible budget
A) is prepared when management
Q79: In the Dichter Co. indirect labor is
Q80: A static budget is not appropriate in
Q81: Top management can control
A) only controllable costs.
B)
Q82: A responsibility report should
A) be prepared in
Q84: Kathleen Corp. produced 320000 units in 150000
Q85: At zero direct labor hours in a
Q86: The accumulation of accounting data on the
Q87: Chambers Inc. uses flexible budgets. At normal
Q88: A company's planned activity level for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents