The Grand Performance Hall is in the process of remodeling and is scheduled to open for business after being closed for 50 years.As part of the remodeling,it is installing a new sound system.The sound system is to be installed by Sound Systems,Inc.on or before April 10.Opening night of the hall is May 1.The contract states that "time is of the essence" because of the opening-night deadline.Sound Systems has some financial difficulties and doesn't deliver the system until April 20.Grand Hall refuses to accept it,and Sound Systems sues.What result?
A) Grand Hall wins; the contract date was strictly enforceable.
B) Sound Systems wins; the contract was substantially performed.
C) Grand Hall wins; there was commercial frustration.
D) Sound Systems wins; there was a true impossibility.
Correct Answer:
Verified
Q23: Identify four factors courts consider in deciding
Q24: A contract between a company in the
Q25: The distinction between a condition precedent and
Q33: In January 2008,Professor Noe entered into a
Q35: Harry agreed to pay $100 to rent
Q37: Sea Rovers,Inc.contracted to sell 1,000 pounds of
Q39: As set forth in the Restatement Second
Q40: Linda agrees to buy Missy's Greyhound race
Q41: Name and describe the types of conditions,explain
Q45: Buddy was hired to play drums for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents