An order for 100 of a product is processed on work center 123. The setup time is 60 minutes and the run time is 5 minutes per piece. If the order is run on two machines in the work center, and the setups are made simultaneously, the elapsed time will be:
A) 560 minutes
B) 500 minutes
C) 250 minutes
D) 310 minutes
Correct Answer:
Verified
Q16: Which of the following files is used
Q17: Work authorization can be classified under the
Q18: Which of the following files will contain
Q19: Which of the following are characteristics of
Q20: A shop order for 1000 pieces is
Q22: If the previous backlog was 20 units,
Q23: Given the following data, which job(s)
Q24: Which of the following dispatching rules ignore
Q25: Given the following information, which sequence
Q26: The planned backlog was:
A) 30
B) 36
C) 40
D)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents