The Last Step in Calculating the Hourly Rate to Be

Question 75

Multiple Choice

The last step in calculating the hourly rate to be charged in time-and-material pricing is to


A) estimate the total labor costs plus fringe benefits.
B) estimate the total labor hours.
C) add a profit margin.
D) add a charge for overhead costs.

Correct Answer:

verifed

Verified