Electric Zero produces relay units for generators.Each relay has a standard cost of $67.Standards call for two relays per generator.In July, the company purchased 120 relays for $7,560.The company used 104 relays in the production of 50 generators, with four relays damaged in the installation process.The standard quantity of labor is 20 hours per generator, with a standard wage rate of $23.In July, the company incurred 1,020 labor hours at a cost of $22,950.How much is the labor rate variance?
A) $460 unfavorable
B) $50 favorable
C) $510 favorable
D) $460 favorable
Correct Answer:
Verified
Q73: Which one of the following is a
Q74: Why is the point of purchase the
Q75: What does an unfavorable overhead volume variance
Q76: Steep, Inc.budgeted 6,000 cup holders for
Q77: Blue Box Beach Chairs has the
Q79: Standard Faucets uses standard costing and
Q80: If the controllable overhead variance is favorable,
Q81: Which of the following variances is most
Q82: Ultimate Production manufactures radon detectors.The standard for
Q83: Sigorny Company uses standard costing and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents