Given the following information about a project:
EV = $20,000
PV = $15,000
AC = $25,000
BAC = $40,000
Estimated Duration = 6 months
Assuming this is the only information available, which of these can we legitimately conclude about the project?
A) Time Estimate at Completion EACtime) ) = 4.5 months.
B) CV = +$5,000
C) Cost Estimate at Completion EACcost) ) = $32,000
D) CPI = 1.33
E) SV% = 1.2
Correct Answer:
Verified
Q1: Given the following information about a project:
EV
Q2: Given the following information about a project
Q4: Given the following information at week 12
Q5: Given the following information at week 19
Q6: Which of the following is/are sources of
Q7: What is the difference between planned value
Q8: Which of the following offers the best
Q9: A project task is scheduled to begin
Q10: A project team has worked for six
Q11: Which of the following project monitoring tools
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents