In Evaluating Time-Cost Tradeoffs, We Start by Crashing the Activity

Question 8

Multiple Choice

In evaluating time-cost tradeoffs, we start by crashing the activity on the critical path that:


A) has the lowest crash cost per unit time.
B) has the lowest total crash cost.
C) can be reduced the most.
D) is the longest.
E) none of the above.