Aye Corp.purchases a remote-site building for computer operations.The building will be suitable for operations after some necessary expenditures.The wiring must be replaced to handle the computer specifications.The roof is leaking and must be replaced.All rooms must be repainted and re-carpeted and there will also be some updating of the plumbing needed.Which of the following statements is true?
A) The cost of the building will include the repainting and re-carpeting costs.
B) The cost of the building will include the cost of replacing the roof.
C) The cost of the building is the purchase price of the building, while the additional expenditures are all capitalized as Building Improvements.
D) The wiring replacement will be part of the computer costs, not the building cost.
Correct Answer:
Verified
Q40: A change in the estimated residual value
Q41: Angus Corp.acquires land for $105,000 cash.Additional costs
Q42: The cost of land does not include
A)closing
Q43: Interest incurred on the construction of a
Q44: The asset turnover indicates how efficiently a
Q46: Which of the following would not be
Q47: Asset retirement costs are
A)added to the cost
Q48: Enmerick Corporation purchases a new delivery truck
Q49: Which of the following is not an
Q50: Land improvements should be depreciated over the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents