Scorpion Production Company planned to use 1 yard of plastic per unit budgeted at $81 a yard. However the plastic actually cost $80 per yard. The company actually made 3900 units although it had planned to make only 3300 units. Total yards used for production were 3960. How much is the total materials variance?
A) $48600 U
B) $4860 U
C) $3960 F
D) $900 U
Correct Answer:
Verified
Q81: The purchasing agent of the Poplin Inc.
Q82: The formula for the materials quantity variance
Q83: A company developed the following per-unit standards
Q84: The standard rate of pay is $20
Q85: If actual costs are greater than standard
Q87: A company purchases 20000 pounds of materials.
Q88: The formula for the materials price variance
Q89: The total variance is $35000. The total
Q90: The standard number of hours that should
Q91: The per-unit standards for direct materials are
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents