If the materials price variance is $600 F and the materials quantity and labour variances are each $450 U, what is the total materials variance?
A) $600 F
B) $450 U
C) $150 F
D) $1,050 U
Correct Answer:
Verified
Q42: Which of the following would generally not
Q43: Use the following information for questions
A company
Q46: An unfavourable materials quantity variance would occur
Q47: Use the following information for questions
Bridgeware
Q48: A company uses 40,000 kilograms of materials
Q50: A company uses 3,150 kilograms of materials
Q54: The most rigorous of all standards is
Q82: The formula for the materials quantity variance
Q95: A total materials variance is analyzed in
Q112: The investigation of a materials quantity variance