The Standard Factory Overhead Rate Is $7 ? What Is the Amount of the Variable Factory Overhead
The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% capacity of 80,000 machine hours.The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: ? What is the amount of the variable factory overhead controllable variance?
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:
Verified
Q151: The standard costs and actual costs
Q152: Based on the following information, calculate
Q153: Based on the following information, calculate
Q154: The _ is the difference between the
Q155: Frogue Corporation uses a standard cost
Q157: Which of the following formulas is used
Q158: The standard factory overhead rate of
Q159: A hotel has 50 suites in total,
Q160: It would be most appropriate to develop
Q161: Brown Inc.'s production budget for Product
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents