Belgium Co. is constructing a tunnel for $600 million. Construction began in 2013 and is estimated to be completed in 2018. At December 31, 2015, Belgium has incurred costs totaling $267 million with $64 million of that incurred in 2015, $107 million in 2014, and the remainder during 2013. Belgium believes that it completed 30% of the tunnel during 2015, although that may change based on future activity. Belgium Co. uses IFRS for its accounting and regards its cost numbers as very uncertain. What amount of revenue should Belgium Co. recognize for the year ended December 31, 2016?


A) No revenue should be recognized until the contract is completed in 2018.
B) $267 million
C) $180 million
D) $64 million

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents