Manchester Ltd Actual Manufacturing Overhead Costs Incurred in December Were £31,000

Question 48

Essay

Manchester Ltd. uses a job-order costing system and a predetermined overhead rate based on machine hours.
At the beginning of the year, the company estimated manufacturing overhead for the year would be £135,000 and 9,000 machine hours would be used.
The following information pertains to December of the current year:  Job No.  Job No.  Job No. 380381382 Totals  Work in process, December 1 £8,000£13,000£19,000£40,000 December production activity:  Materials requisitioned £2,000£2,400£3,600£8,000 Direct labour costs £1,200£1,800£2,000£5,000 Machine hours 4007009002,000\begin{array}{lrrrr}&\text { Job No. } & \text { Job No. } & \text { Job No. } & \\&380 & \underline{381} & \underline{382} & \text { Totals } \\\hline\text { Work in process, December 1 } & £ 8,000 & £ 13,000 & £ 19,000 & £ 40,000 \\\text { December production activity: } & & & & \\\text { Materials requisitioned } & £ 2,000 & £ 2,400 & £ 3,600 & £ 8,000 \\\text { Direct labour costs } & £ 1,200 & £ 1,800 & £ 2,000 & £ 5,000 \\\text { Machine hours } & 400 & 700 & 900 & 2,000\end{array} Actual manufacturing overhead costs incurred in December were £31,000.
a.Compute the predetermined overhead application rate.
b.Determine the total cost associated with each job.

Correct Answer:

verifed

Verified

None...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents