Cheng Inc.is considering a capital budgeting project that has an expected return of 25% and a standard deviation of 30%.What is the project's coefficient of variation?
A) 1.20
B) 1.26
C) 1.32
D) 1.39
E) 1.46
Correct Answer:
Verified