Use the Following Information for Questions

Question 66

Multiple Choice

Use the following information for questions:
Streetside Construction agreed to build a shopping centre for $25,000,000 over the next four years.Estimated cost for years one through four are: $7,500,000; $5,000,000; $5,000,000; and $2,500,000.
-Assume total estimated costs to complete the job at the beginning of year three were revised to $27,000,000.If actual costs in year four were equal to those revised estimated costs, and the completed contract method were used, what would be the profit or loss recognized in year four?


A) $ -0-
B) $2,000,000)
C) $3,000,000
D) $1,000,000)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents