If an Overall Loss Is Projected on a Long-Term Construction

Question 43

Multiple Choice

If an overall loss is projected on a long-term construction project, when is it recognized under the percentage of completion method?


A) In the period it occurred
B) In the period it was estimated
C) In the last period of the job
D) In each period the job is in process