What is the formula for the earliest finish time for activity i?
A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi-1 + ti
D) EFTi = ESTi - ti
Correct Answer:
Verified
Q5: Exhibit 14.13
The following questions use the information
Q18: Slack for activity I is computed as
A)LFTi
Q20: Exhibit 14.13
The following questions use the information
Q21: Which activities have slack in the following
Q24: Exhibit 15.2
The following questions employ the AON
Q26: Exhibit 15.2
The following questions employ the AON
Q42: Exhibit 15.1
The following questions employ the AON
Q47: Exhibit 15.2
The following questions employ the AON
Q48: The critical path is the _ path
Q58: If we are employing Activity-On-Arc (AOA) network