Question 19

Multiple Choice

A company wants to select no more than 2 projects from a set of 4 possible projects. Which of the following constraints ensures that no more than 2 will be selected?


A) X1 + X2 + X3 + X4 = 2
B) X1 + X2 + X3 + X4 \le 2
C) X1 + X2 + X3 + X4 \ge 2
D) X1 + X2 + X3 + X4 \ge 0

Correct Answer: