Two Government Projects Have the Following Benefit Profiles

Question 3

Multiple Choice

Two government projects have the following benefit profiles:
Two government projects have the following benefit profiles:   -Which of the following statements is accurate? A)  Because the combined benefits of the two projects over the four years each equals 160,000, the net present value of the projects will be equal. B)  Because the sum of benefits 160,000)  exceeds the investment cost 100,000)  for both projects, the net present value of both projects will always be positive. C)  The net present value of Project A becomes negative at a higher discount rate than does the net present value of Project B D)  The net present value of Project B becomes negative at a higher discount rate than does the net present value of Project A
-Which of the following statements is accurate?


A) Because the combined benefits of the two projects over the four years each equals 160,000, the net present value of the projects will be equal.
B) Because the sum of benefits 160,000) exceeds the investment cost 100,000) for both projects, the net present value of both projects will always be positive.
C) The net present value of Project A becomes negative at a higher discount rate than does the net present value of Project B
D) The net present value of Project B becomes negative at a higher discount rate than does the net present value of Project A

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents