Activity C is an immediate predecessor of activity G.Both activities have 4 hours of slack time.If both activities are delayed 3 hours, and these are the only delays, the overall effect of these delays is to delay the minimum project completion time by:
A) 0 hours.
B) 2 hours.
C) 6 hours.
D) The overall delay cannot be determined with only this information.
Correct Answer:
Verified
Q25: A "forward pass" in network analysis of
Q26: Which of the following is true?
A)PERT gives
Q27: The probabilistic approach characterized by PERT does
Q28: Discuss the assumptions required for determining the
Q29: In the PERT probabilistic approach, statisticians have
Q31: Ajax is about to embark on
Q32: A project contains activities D and K.Activity
Q33: Which of the following is not a
Q34: PERT/Cost is a cost-center based system, where
Q35: PERT/Cost:
A)allows for activity interruption.
B)assumes costs are evenly
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents