Solved

GoodFriend Inc What Is the Probability That the Project Can Be Completed

Question 43

Essay

GoodFriend Inc.plans to upgrade its accounting software.The main activities for the project are:A.Evaluate available products.
B.Determine the hardware requirements.
C.Order and obtain the hardware.
D.Order and obtain the software.
E.Set up the hardware.
F.Train the IT staff to implement and support the software.
G.Train the end users.
H.Install the software.
I.Customize the software.
J.Test the system.
The following table indicates the PERT estimates in work days.
 Job Predecessorsoptimistic Most Likely Pessimistic  A 102030 B 235 C  B 5810 D  A 3510 E  C 124 F  D 5715 G  D 5715 H  E, F 124 I  H 152030 J  G. I 41015\begin{array}{ccccc}\text { Job}&\text { Predecessors}&\text {optimistic}&\text { Most Likely}&\text { Pessimistic }\\\text { A } & -- & 10 & 20 & 30 \\\text { B } & -- & 2 & 3 & 5 \\\text { C } & \text { B } & 5 & 8 & 10 \\\text { D } & \text { A } & 3 & 5 & 10 \\\text { E } & \text { C } & 1 & 2 & 4 \\\text { F } & \text { D } & 5 & 7 & 15 \\\text { G } & \text { D } & 5 & 7 & 15 \\\text { H } & \text { E, F } & 1 & 2 & 4 \\\text { I } & \text { H } & 15 & 20 & 30 \\\text { J } & \text { G. I } & 4 & 10 & 15\end{array}
What is the probability that the project can be completed in 65 work days?

Correct Answer:

verifed

Verified


Use Crystal Ball to solve the problem.F...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents