In Microsoft Project, the Correct Sequence of Defining a Project's

Question 18

Multiple Choice

In Microsoft Project, the correct sequence of defining a project's working time is:


A) select calendar template, manipulate days of the week, specify number of hours per day, specify non- working time, and verify calendar.
B) select calendar template, specify non- working time, manipulate days of the week, specify number of hours per day, and verify calendar.
C) select calendar template, specify non- working time, specify number of hours per day, manipulate days of the week, and verify calendar.
D) select calendar template, manipulate days of the week, specify non- working time, specify number of hours per day, and verify calendar.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents