The most time- consuming method of tracking progress in Microsoft Project is:
A) always track by entering the percent of work complete.
B) always track by entering the actual work done and work remaining.
C) always track by entering the percent of work remaining.
D) always track by entering the hours of work done per time period.
Correct Answer:
Verified
Q1: By default, every task in Microsoft Project
Q2: For task durations, the default in Microsoft
Q3: In Microsoft Project, defining the project's working
Q4: What is NOT among the calendar templates
Q5: Microsoft Project determines the start and finish
Q7: In the earned value report, Microsoft Project
Q8: The default view in Microsoft Project is
Q9: Which dependency option is NOT available in
Q10: What is not among the options in
Q11: In the earned value report, Microsoft Project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents