A diagram that shows the ordering of activities by connecting predecessor and successor tasks is called a:
A) Gantt chart.
B) Work breakdown structure.
C) Predecessor- successor diagram.
D) Network diagram.
Correct Answer:
Verified
Q16: Projects are:
A)indefinite.
B)never successful.
C)temporary.
D)to be avoided.
Q17: A method used for determining the sequence
Q18: During the _process, potential projects are identified
Q19: During the_ process, scope, time, cost, and
Q20: All of the following are examples of
Q22: Errors made when estimating the expecting or
Q23: The project management core area including organizational
Q24: During the _process, all paper work is
Q25: The project management core area including communications
Q26: The project management core area including solicitation,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents