The _________is the ratio of EV to PV.
A) schedule performance ratio
B) cost performance ratio
C) schedule performance index
D) cost performance index
Correct Answer:
Verified
Q17: All of the following are philosophies of
Q18: For relatively small projects, the_ may be
Q19: The_ is a time- phased budget that
Q20: The _is the ratio of EV to
Q21: _are documented and authorized changes that are
Q23: A post- implementation review is conducted:
A)a few
Q24: A_ is a systematic and formal enquiry
Q25: _are approved and authorized actions that are
Q26: _is the difference between the scheduled completion
Q27: A cost control method for examining project