What is NOT true about technical risks of information systems development projects?
A) A project is less risky if the user group is familiar with the systems development process than when the user group is unfamiliar with the process.
B) Large projects are riskier than small projects.
C) Systems with flexible requirements are less risky than projects with highly structured requirements.
D) The development of systems using standard methodologies is less risky than the development of systems using novel technology.
Correct Answer:
Verified
Q8: Rental of space and equipment is an
Q9: The process of analyzing an organization's activities
Q10: Which of the following is NOT one
Q11: Which of the following is NOT an
Q12: When identifying the financial benefits and costs
Q14: _is the process of progressively elaborating and
Q15: What is NOT a characteristic of information
Q16: The process of assessing the degree to
Q17: The introduction section of the baseline project
Q18: Operational inefficiency is an example of:
A)intangible benefits.
B)intangible
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents