When defining activities, a sufficient level of detail is reached when:
A) it has been broken down by three levels.
B) an activity has a known method or technique.
C) each activity is very small.
D) all activities are on the same level.
Correct Answer:
Verified
Q30: Schedules are:
A)often updated t incorporate project changes.
B)important
Q31: Work packages should be all EXCEPT:
A)completed by
Q32: Higher level components that are broken down
Q33: _is the time required by one task
Q34: A diagramming method using arrows to represent
Q36: The need to collect requirements before completing
Q37: Schedules are:
A)rarely perfect.
B)useless.
C)easy to develop.
D)made to be
Q38: _dependencies indicate the relationship of project activities
Q39: The need to back up important data
Q40: A schematic display that illustrates the various
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents