Total slack is the time an activity can be delayed without affecting the immediately following activity.
Correct Answer:
Verified
Q97: In contrast to the critical path method,
Q98: In critical chain scheduling, a project buffer
Q99: An example of parametric estimating is the
Q100: Total slack is also known as _
Q101: Duration is the actual time spent working
Q103: Human resources include all project stakeholders.
Q104: In information systems projects, only the development
Q105: In terms of project time management, resource
Q106: For experienced project managers, it is okay
Q107: When managers choose one resource over others,