The Critical Path Method Determines the Sequence of Task Activities

Question 47

Multiple Choice

The critical path method determines the sequence of task activities that directly affect the completion of a project by:


A) determining the longest path through a network diagram.
B) subtracting the shortest path from the longest path in a network diagram.
C) adding all activities in a network diagram.
D) determining the shortest path through a network diagram.

Correct Answer:

verifed

Verified