The performance of activities in parallel that would normally be performed in sequence in an attempt to shorten the duration of a project is called:
A) crashing.
B) schedule compression.
C) fast- tracking.
D) PERT.
Correct Answer:
Verified
Q33: Resource allocation:
A)plays a large role in determining
Q34: The longest path through a network diagram
Q35: The process of determining start and finish
Q36: _ is an estimating technique in
Q37: The use of mathematical techniques to shorten
Q39: _ is the measure of the
Q40: The process of putting procedures and rules
Q41: _ slack is the time and
Q42: The prudent project manager should provide
Q43: Resource leveling heuristics are _ used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents