The actual time spent working on an activity, not accounting for any breaks, is called:
A) length.
B) time.
C) effort.
D) duration.
Correct Answer:
Verified
Q2: Any activity on the critical path:
A)contains total
Q3: The elapsed time between start and finish
Q4: The process used to determine the magnitude
Q5: The time an activity can be delayed
Q6: All of the following are techniques for
Q8: _ is any form of network
Q9: A _ is a control system developed
Q10: The _ is a dedicated part
Q11: A _ contains data and information
Q12: The estimation of activities' durations based upon
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents