The estimation based on the experience of one or more experts on the particular activity or project is called:
A) published estimating data.
B) expert judgment.
C) bottom- up estimating.
D) alternatives analysis.
Correct Answer:
Verified
Q11: A _ contains data and information
Q12: The estimation of activities' durations based upon
Q13: Dates imposed to meet some type of
Q14: The critical path in a network diagram
Q15: Hard data from specific activities carried out
Q17: The sequence of activities:
A)can be determined without
Q18: In information systems development projects, _
Q19: The time an activity can be delayed
Q20: _ is an estimating technique in
Q21: Managing resources should be considered:
A)during execution of