All of the following are elements of a risk response plan EXCEPT:
A) a list of actions to be used to implement the risk response strategies.
B) the roles and responsibilities of any risk owners.
C) budget and schedule information in terms of risk response.
D) the roles and responsibilities of project stakeholders.
Correct Answer:
Verified
Q18: Risk management planning meetings should be attended
Q19: _is a tool used to determine whether
Q20: The process of developing methods for responding
Q21: _is a technique to examine the potential
Q22: The most well- known simulation technique is
Q24: Tornado analysis is a form of:
A)EMV analysis.
B)graphical
Q25: Changing industry standards are an example of:
A)external
Q26: The systematic approach to planning the risk
Q27: Poor project planning is an example of:
A)project
Q28: _is a statistical technique that captures the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents