Typical problems faced by software developers when estimating project schedules include:
A) forgetting to account for sick leaves, vacations, training time in the project schedule.
B) developers getting discouraged by frequent changes to the project schedule.
C) managers wanting to reduce the proposed time frame.
D) all of the above.
Correct Answer:
Verified