A contractor and Buckingham, Inc.have a contract, which calls for the contractor to build a building with the completion of it by June 15.If the building is not completed by that date, the contract calls for the contractor to pay $100 per day in damages.The $100 per day is:
A) punitive damages.
B) nominal damages.
C) liquidated damages.
D) an illegal penalty.
Correct Answer:
Verified
Q7: When a breach of contract occurs,the nonbreaching
Q11: Equitable remedies are available any time the
Q17: Restitution involves a return of consideration or
Q21: Even if a party has the power
Q25: Lost profits can never be recovered as
Q28: The expectation interest is protected by the
Q29: If a liquidated damage provision is found
Q29: Courts of equity will grant specific performance
Q38: Costs incurred to acquire a nondelivered performance
Q39: Monetary damages are the most frequently granted
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents