Automan, Inc. makes "tennis robots" on an assembly line with 9 tasks. The tasks and their times follow. The desired output rate is 50 robots an hour. The "theoretical maximum efficiency" on the line is
A) less than 85%.
B) more than 85% but less than or equal to 90%.
C) more than 90% but less than or equal to 95%.
D) more than 95%.
Correct Answer:
Verified
Q1: Consider the location of four distribution
Q2: A single facility is needed to
Q4: What is the definition of "theoretical maximum
Q5: An assembly line has to perform
Q6: McKenna Restaurant wishes to open a
Q7: Build- It- Fast Inc. is analyzing the
Q8: Which of the following statements about performance
Q9: Table 10.5
Union Fork, Inc. has five
Q10: Which one of the following is usually
Q11: Table 10.2
Durham Toy, Inc. has five
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents