Assuming a beta distribution is being used, if the most optimistic time for an activity decreases by 12 days, what will happen to the expected time for that activity?
A) It will decrease by 12 days.
B) It will increase by 2 days.
C) It will decrease by 2 days.
D) It will remain the same.
Correct Answer:
Verified
Q1: To calculate the probability of completing a
Q3: In making an estimate of the most
Q4: Which one of the following conditions violates
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,