A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity. What are the duration and the early start time associated with this hammock activity?
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
Correct Answer:
Verified
Q75: The least amount of float is found:
A)In
Q79: A project has the precedence requirements and
Q80: Use the information in the table to
Q85: A gentleman farmer maniacally works on academic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents