An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?
A) Less than 31 days but greater than or equal to 29 days
B) Less than 29 days but greater than or equal to 27 days
C) Less than 27 days but greater than or equal to 25 days
D) Less than 25 days
Correct Answer:
Verified
Q17: A backward pass is performed when it
Q18: One of the defining points of a
Q19: Draw a network of any size that
Q20: An activity has an expected duration and
Q21: Preceding activities are those that must occur
Q23: The length of time expected to complete
Q24: An activity has an optimistic time estimate
Q25: Project Test Bank is composed of
Q26: At a merge point in a forward
Q27: Project Test Bank is composed of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents