Solved

The Term Ordered Activity Means

Question 15

Multiple Choice

The term ordered activity means:


A) Tasks must either precede or follow other tasks in project planning and management.
B) Tasks cannot be performed unless the project manager issues a specific command to perform the work.
C) Prior project planning removes the need for any rush so that tasks can be performed in a methodical fashion.
D) Tasks are not performed unless the customer issues a specific request to perform the work.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents