Multiple Choice
Which statement about this Gantt chart is BEST?
A) Activity a has a duration that could be as short as 1 day and as long as 10.
B) Activity b probably has activity a as a predecessor.
C) No progress has been made on activity c.
D) Activity d is the longest activity.
Correct Answer:
Verified
Related Questions
Q3: The least common type of lag relationship
Q6: Sketch a network and use it as
Q7: A finish to start lag delay is