A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach.
A) 8.5 days
B) 17 days
C) 24.5 days
D) 34 days
Correct Answer:
Verified
Q48: List any three criticisms of critical chain
Q61: A project is represented by the activity
Q62: A project is represented by the activity
Q63: A project is represented by the activity
Q64: A project consists of six consecutive tasks
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q67: A project consists of six consecutive tasks
Q68: A project is represented by the activity
Q69: A project is represented by the activity
Q77: The buffers supplied to non-critical paths in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents